Mess Room Completed – April 2015
Mess room, looking forward completed apart from one or two small additions. Mess room looking aft. Mess stove replaced by flame effect convector unit and door replaced. All furniture custom made by Moss Marine
Coming along – March 2015
Replacement Plates – February 2015
Affected area has that has been removed, exposing the chain locker to daylight for the first time in nearly 60 years. Same area with the replacement plate in place. Note that a section of the bulkhead has been removed, as it was a requirement that the replacement went beyond the bulkhead by 150 mm.
Start of the work – January 2015
Over the winter months we have started internal refurbishment on the ship including in the Crew Mess and the Electic Workshop.
The Crew Mess is in the process of being stripped out. Various areas of steelwork seeing daylight for the first time in 25 years!